Construction Update

Property Highlights

Picture2
  • 8.59 acres flat land with no flood zone.
  • Located in the heart of the City of Snellville, on a four lane Centerville Highway
  • Land area big enough to build Masjid, event hall and Gymnasium
Picture3
  • No issues with the neighbors and county
  • Easy access
  • LAND PAID OFF Alhumdolillah
Picture4
  • On the Bible Belt, between 18 churches
  • Only Masjid in the city
  • No Masjid in 10 mile radius
Picture1
  • Civil Site Design completed and Land Development Permit (LDP) plan approved by Gwinnett County on 05/25/2017 after 2.5 years of efforts and coasted approximately 150k (Including all planning, design & approvals)
  • Ground breaking was done on 15th Ramadan 2017
  • LDP has to be completed in one year otherwise permit will be canceled and need to be reapplied
  • Shared driveway with neighbor approved

Ground Breaking Ceremony

County Permit

Picture6

SILT FENCE

Picture7

Complications

Picture8
  • One year permit expired on May 25th 2018 but construction could not start due to insufficient funds.
  • Construction companies require minimum of 70% of total cost to start the project.
Picture9
  • By the grace of Allah (SWT) when we collected 70% of the total cost for contractor to start, mean while county told us to revise the retaining wall design before permit extension.
  • Back and forth with county to revise and getting wall approval with permit extinction took 4-5 months in total.

Permit Extension

Picture10

LDP Work Started

Picture12
  • LDP Construction work started on Dec 15th 2018 by the grace of Allah (SWT).
  • Land mobilized
  • All trees have been cut.

Construction Update