Located in the heart of the City of Snellville, on a four lane Centerville Highway
Land area big enough to build Masjid, event hall and Gymnasium
No issues with the neighbors and county
Easy access
LAND PAID OFF Alhumdolillah
On the Bible Belt, between 18 churches
Only Masjid in the city
No Masjid in 10 mile radius
Civil Site Design completed and Land Development Permit (LDP) plan approved by Gwinnett County on 05/25/2017 after 2.5 years of efforts and coasted approximately 150k (Including all planning, design & approvals)
Ground breaking was done on 15th Ramadan 2017
LDP has to be completed in one year otherwise permit will be canceled and need to be reapplied
Shared driveway with neighbor approved
Ground Breaking Ceremony
County Permit
SILT FENCE
Complications
One year permit expired on May 25th 2018 but construction could not start due to insufficient funds.
Construction companies require minimum of 70% of total cost to start the project.
By the grace of Allah (SWT) when we collected 70% of the total cost for contractor to start, mean while county told us to revise the retaining wall design before permit extension.
Back and forth with county to revise and getting wall approval with permit extinction took 4-5 months in total.
Permit Extension
LDP Work Started
LDP Construction work started on Dec 15th 2018 by the grace of Allah (SWT).